The hottest Rizhao road construction plan in 2017

2022-08-20
  • Detail

Rizhao 2017 road construction plan released six new projects

Rizhao 2017 road construction plan released six new projects

China Construction machinery information

recently, Rizhao Municipal government released the "Rizhao 2017 urban planning and construction management plan and road construction plan", of which, the implementation plan of key national and provincial road construction projects plans to implement an investment of 4.55 billion yuan in 2017, with a total of 10 main construction contents, including, There are 3 expressways, 4 collaborative operation and reconstruction of new and different parts of ordinary national and provincial roads, and 3 large and medium-sized maintenance, with a total mileage of 284 kilometers. The central and provincial investment is 2.43 billion yuan, and the local support is 2.12 billion yuan, including renewal, new construction and preliminary work projects

continue to build two expressways and two national highways

in 2017, a total of four projects were continued, including two expressways and two new reconstruction projects of ordinary national and provincial roads, with a cumulative mileage of 159 kilometers and a continued investment of 3.05 billion yuan

among them, the construction period of the project in Rizhao section of Wei RI expressway is years, of which 1.44 billion yuan has been completed in 2016 and 1 billion yuan is planned to be completed in 2017

Rizhao airport Shenyang Haikou Expressway link. In 2016, 160million yuan was completed, and the remaining investment of 280million yuan was completed and opened to traffic in 2017

reconstruction project of Rizhao section of Yantai Shantou line of national highway 206. It is planned to complete the remaining investment of 760million yuan and open to traffic in 2017

222 provincial highway central Jiangxi line Rizhao Weifang boundary to West Lake reconstruction project. It is planned to complete the remaining investment of 1.01 billion yuan and open to traffic in 2017

6 new projects

a total of 6 new projects started in 2017, including 1 expressway, 2 new reconstruction projects of ordinary national and provincial roads, and 3 maintenance and medium-sized maintenance projects, with a total mileage of 125.4 kilometers. The total investment of the project is 2.93 billion yuan, and the investment is planned to be completed in 2017 by 1.5 billion yuan

lanluo expressway. The Rizhao section of LAN Luo expressway is 6.5 kilometers long, with two-way four lanes, and the subgrade is 27 meters wide. The total investment is 500 million yuan. It is planned to complete the investment of 100 million yuan in 2017 and open to traffic in 2019

reconstruction project of Rizhao Beltway section of national highway 204. The Rizhao belt section of national highway 204 is 32.3 kilometers long, bypassing Rizhao urban area along the west side of Shenyang Hainan expressway, passing through four districts and counties, including Shanhaitian tourist resort, Donggang, Lanshan and Rizhao Economic and Technological Development Zone. The total investment of the project is 1.4 billion yuan. It is planned to start construction in 2017 and open to traffic in 2018

s313 reconstruction project of Ju County ring section of Teng line. The 31.3-kilometer-long Juxian ring road section of provincial highway 313 is around the urban area of Juxian County. The total investment of the project is 840million yuan. It is planned to start construction in 2017 and open to traffic in 2018

large and medium-sized maintenance projects. In 2017, three large and medium-sized maintenance projects were implemented, including the medium maintenance of Rizhao urban section of provincial highway 313 and Ju county urban section, the medium maintenance of Rizhao section of landing line of national highway 518, and the overhaul of Rizhao section of jiaohai line of national highway 341. The total mileage of pre lubrication was 55.3 kilometers, with a total investment of 190million yuan (the central and provincial investment was 160million yuan, and the local supporting investment was 30million yuan). It is planned to be completed in 2017

provincial reconstruction of 12 county and township roads

the construction of county and township roads in the northwest regions of northern Ju, Lianxi and Gangxi LAN is planned to invest 68.23 million yuan in 2017 to complete the upgrading and reconstruction of 12 county and township roads of 98.16 kilometers

including the new connecting road from Baobao to Kushan, the new connecting project from Hengshan to mengtuan in Dongguan (Dongguan outer connecting project), the reconstruction project of the connecting line from Dongguan to national highway 206, the upgrading and reconstruction project of the Ango line, the special road for building materials, the new construction project of the auxiliary road of Qingfengling reservoir, the upgrading and reconstruction project of the Yanzhuang Luohe section of Ju Road, the upgrading and reconstruction project of the senior management line of the connecting project of the new zhaoluo line, Road upgrading and reconstruction project of Wulian section of Dazhu line, Chaoshi Road north extension construction project, and Jubei line overhaul project

port collection and distribution road construction plan

in 2017, it is planned to invest 250million yuan to transform and build 9.2 kilometers of port collection and distribution roads. Beijing Road Shanghai Road Port unblocked project: the reconstruction mileage is 7.6 kilometers, and the estimated investment is 160million yuan. Shenzhen Road East Extension Project: the new mileage is 1.6km, and a two-way six lane project is proposed, with an estimated investment of 90million yuan

"village highway demonstration county" project construction plan

in 2017, it is planned to invest 246.8997 million yuan to transform 412.37 kilometers of village highway, including 253.36 kilometers of Donggang District, with an investment of 150.66 million yuan; Lanshan district is 159.01 kilometers long, with an investment of 96.2397 million yuan

it is worth noting that 103million yuan is planned to be invested to overhaul 200 kilometers of rural roads in 2017. Each district and county government (Management Committee) shall organize the implementation respectively

tourism channel improvement plan. It is planned to build tourism circular channels in Chaohe, kooguan, Hubu, Songbai and street areas of Wulian County, and at the same time, build supporting bicycle greenways, with a planned investment of 140million yuan. Organized and implemented by Wulian County Government